The tie-in of the new permanent lines for the temporary chiller was completed last week.
The old chillers, compressors, and piping have been removed. The concrete pad for the new chiller has been extended. The area is ready for the new equipment.
The parts piles have grown and include the signage for tomorrow's street closing due to the planned arrival of a crane and the new equipment.
A platform has been built through where the door from the penthouse to the lower roof used to be. The new chiller will be brought in through that opening.