Thursday, December 22, 2011

Chiller replacement - 7

The 60-ton temporary chiller arrived today. It was quite an ordeal to get it unloaded from the delivery truck and placed on the back of the crane truck.



The crane truck was then turned around so that the temporary chiller could be placed near where it will be hooked up next week. By early afternoon the temporary chiller was at its final resting spot for today.



The six 5-ton portable coolers also arrived today but at the same time the temporary chiller was being unloaded. As a result, the portable coolers had to be unloaded on a nearby side street.